|
TAPE 12 of 16,
SIDE B
A schedule comparison
of the CH-53A with the CH-53E should be instructive. If you compare the two
programs, the E obviously took years longer. In fact the first production
E was the fifth actual aircraft built. It was delivered some nine years after
go-ahead while the fifth A was delivered in less than two years from go-ahead.
The four-year delay in getting the E started was about four times as long
as the delay introduced in the 53A program by those in OSD who forced the
poorly conceived Tri-Service Transport Program on the services. Again, it's
not the right way to buy aircraft.
To finish up the HLH,
the Army went ahead with its Vertol design, but advertised it as only a technology
program, with some calling it a prototype program. In their Congressional
testimony, they claimed they had made no cost estimates of either the engineering
development or production. This caused them all kinds of trouble in Congress
of course and why they took that tack I'll never know. If they had never
made any cost estimates as they claimed they should never have been allowed
to get started and all the delays could have been avoided. They ran the program
for a while, let an engine contract, but eventually cancelled the program
after a year or two. I think that probably ends my official involvement with
helicopters. I had retired before the Black Hawk and the UTTAS came along.
Those were programs that probably should have ended up by replacing the
CH-46 as well. A replacement for the 46 could have been a marinized version
of the Army's Blackhawk.
Now that we've cleaned
up the HLH situation and looking back at our chart of
Navy starts it looks like
we've pretty well finished them up with a few exceptions. The EA-6B in 1966
was a fairly straightforward modification of the A-6 to get a countermeasures
version and made a four-place airplane from a two-place airplane and a completely
new avionics suit of course. It's hardly worth talking about though and I
have nothing to add to the story other than it was the most efficient way
to achieve the capability.
In '68 we bought the Jet
Ranger as a new helicopter trainer. First time in a long time we bought a
new helicopter trainer and that was straightforward. Not much of a story
there.
In '69 we started the
F-14 and S-3. We skipped over the F-111 and the TFX and because that ties
in with the F-14. I'll skip that again for the time being, but let's finish
off the S-3 which will then complete our chart which takes us up through
1969. We had long needed a replacement for the S-2, and for at least ten
years studies had been performed trying to get a configuration and an ASW
system that offered enough improvement over the S-2 to be able to justify
the development. Most of the studies during that time were done using turbo-prop
T-64 engines but there was never enough advantage shown by doing a slightly
new air frame and without having enough of an advance in the ASW system
itself. Finally in the period from the mid-sixties on system improvements
came along. As I recall, the studies were done at Johnsville putting together
new systems for both the P-3 and for a carrier-based ASW airplane. Simultaneously,
a high bypass ratio fan engine was started, the TF-34, at General Electric.
The combination of those two developments allowed us to finally get to the
point where we could justify a new ASW carrier-based airplane. The period
was one in which major justification studies had to be done. I was not involved
to any degree in those, but I believe that a good many of them were done
as funded studies. At the time there was an ASW office in OPNAV that coordinated
all the ASW activities and all of the NAVAIR system studies had to be coordinated
with that office. Probably the major players in the airplane side of the
game at least during that period were Grumman, Lockheed and Douglas. They
all had funded studies and as I said I really wasn't involved to any great
degree.
When the program finally
got approved a few months after the F-14s then obviously I did get involved
and we started the total acquisition process. Things went a great deal slower
than was necessary mostly because of the changes in the acquisition system
coming down from OSD. In the past we had been either ignoring or working
our way around such directions without really changing our system. In this
case we had a new program manager. He was new to the bureau, or rather, new
to the System Command as we had been renamed. (I'll probably continue calling
it bureau because it's easier to say.) He was a Navy captain, Pete Elliot.
He had brought along a civilian who had been a Navy electronics technician
with him in the fleet, Don Lewis. Both of them were well qualified in the
ASW game and certainly knew what they were doing. The problem the new program
manager had however was that not knowing the background of all of the fights
in the system acquisition business. He tended to believe the OSD directives
rather than ignoring them as I, at least, consciously did. He was afraid
that the DDR&E and company then would not approve the whole program unless
he followed the "book" in every respect. So the RFP got to be a two inch
thick document instead of the normal quarter of an inch thick document. It
was a word game, took time and whatnot. We really kept our sanity pretty
well.
At the same time we had
a new CNM, Adm. Galantin who was a submariner who had virtually no background
in the air side of the game, didn't understand our system and he tried to
make us do things more like the "book" too rather than "our" way.
When the system was finally
set up rather than defining the ASW system completely the door was left
open so that the contractors could do their own definition of the total system.
There were specs set out for many parts of the system but putting it all together
was really not done in this case so we ended up running simultaneously an
air frame competition and an ASW system competition.
Probably when we get around
to talking source selection and acquisition procedures you'll find out that
I really tried to run aircraft competitions by defining everything that we
could so that basically we ended up running only an air frame competition.
And the reason for that obviously was we knew how to do that and it was a
lot tougher to try to do a competition in which you had two major variables.
The program was finally
outlined and as set down in the RFP was that we would have a competition.
We'd select two contractors initially for a competitive period and eventually
settle down to one. I can't remember the details of what we told them about
how that was to go but that was the general scheme. We had trouble with Adm.
Galantin who wanted us to quantify our selection criteria which we had never
done in the past. We had always claimed that all we had to do was buy the
best airplane, and justify our selection by telling everyone why we thought
so, in engineering terminology.
When we talked to Galantin
I tried to convince him that we knew what we were doing, we had a good record
but he still made us give some kind of quantification to the criteria so
we gave him some lip service by saying that the most important factor was
"technical" and with less important -- it's really not less important but
we told him it was -- items of "logistics", "management", and "cost". He
was finally satisfied and we finally got the RFP out.
As I said, the competition
was really in two parts, the air frame and the ASW system. In this case the
program manager Pete Elliot and Don Lewis, together with the electronics
division pretty much handled the evaluation of the ASW system and came up
with their rankings of the systems involved in the various airplanes. I concentrated
as usual on the air frame part of the game using our conventional methods
with all the divisions being involved.
We were lucky in that
Lockheed came up to be first in the air frame part of the competition as
well as first in the ASW system part so we didn't have any problem in determining
the winner. Well, the business of Lockheed ending up as number one for a carrier-based
airplane I think startled some people. It certainly wouldn't have happened
if they had not had Vought as a partner. It was a teamed arrangement. Watching
the preliminary design studies of Lockheed's over the years for carrier-based
designs I believed that they would never win a competition by themselves
because of a lack of experience in that field. As soon as they signed up
Vought and Vought started doing the airplane part of the game they became
much more competitive. Vought of course had a long background in carrier-based
airplanes.
The number two airplane
surprising to us was General Dynamics but they were definitely a better overall
second choice than the others. McDonnell Douglas air frame had really been
knocked out on flying qualities counts and Grumman just didn't quite measure
up in either the air frame or in the ASW system. Well, the choice to us was
clear-cut enough at that time that we tried to get CNM Adm. Galantin to go
along with the idea of skipping the second definition phase of defining the
airplane but to go ahead and just finish up doing the job with one contractor.
But he was unwilling to do that and directed us to go ahead with the way
the book was written since that was how DDR&E had approved the program.
So we had to go through the second step. I'm quite sure that had to be funded
and when you have to fund, when you have to sit down and negotiate and write
a contract for just a portion of the whole game, it takes time, costs money
and really isn't necessary.
I suppose I should mention
the reason for why GD was surprising. They had not really done much in the
way of carrier-based design other than the TFX. They were afraid that the
stigma of the TFX had so branded them in NAVAIR's mind that they wouldn't
get a fair shake in the competition. They were sure we'd throw them out just
as soon as we saw the nameplate. But we really didn't play the game that
way. After the final decision was made in favor of Lockheed we had a letter
from General Dynamics to the Commander of the Air Systems Command really
congratulating us on running a fair competition.
As I already indicated,
Lockheed won that second phase of the competition. I suppose that was close
to what they now talk about as "best and final offer" although it went on
longer and was less of a bidding contest. Before we were able to announce
Lockheed as a winner however we ran into a complication with our own CNM
financial people and our secretary for logistics or whatever he was called,
I&L of Financial Management maybe, questioning whether or not Lockheed
was in any financial condition to undertake a contract. The Air Force C-5
had Lockheed in trouble. They were getting guaranteed loans from the government.
It obviously became then something that the managers on high could question
since they were usually not in a position to question anything else. That
held us up for quite a while. We had to show the differences between our
kind of a contract and the C-5 contract.
Just as an aside on all
this for those that don't know the story the C-5 really got in trouble right
from the start in that competition run by the Air Force, and reported in
a congressional hearing. It appeared that the Boeing design had won the C-5
competition, and that decision got overturned by the Secretary of the Air
Force or OSD, I can't remember which one, primarily because Lockheed had
a lower price than the Boeing. Unfortunately, however, there was a reason
for the difference in price. The Lockheed airplane was a little too small
but the decision went to Lockheed and then they were pressured by the higher
ups in Defense Department to "not change their cost" while increasing the
aircraft size by something like ten percent. They made a lot of other changes
but they were held to that original cost quotation. In addition, the whole
procurement was done under a contracting scheme called Total Package Procurement,
and that didn't help either. In Total Package Procurement the air frame contractor
is held responsible for buying the engines and the equipment that's usually
GFE where the government would take the responsibility if any of those items
went overweight or over cost. Even then Lockheed would have been all right
financially if the Air Force had bought all the items that were initially
on the contract. As I recall there were three lots, lots A, B, and C. They
had actually bought the first two, lots A and B, and they had given Lockheed
a letter of intent for the last and big lot. At the time of their financial
crisis that contract had not been definitized. Well, the way the contract
was set up each lot was priced, but included a correction factor for the
actual price of the preceding ones. And if you worked out the mathematics
of what the contract called for, the loss on the final contract, if they
had bought all the airplanes , would have been minimal and would not have
caused a problem for the contractor. But since they never reached that point
Lockheed found themselves unable to proceed without getting some loans that
had to be guaranteed by the government. Eventually they all got repaid of
course and the government made money on the deal.
Well our contract on the
S-3 was going to be a fixed price incentive contract for the R&D quantity,
I think it was nine airplanes, and then fixed price ceiling options for a
total buy of up to 200 aircraft and with variable lot pricing included through
all of the lots. It's a tough kind of a contract and one that gives an overwhelming
advantage to the government. We got that contract all negotiated and were
ready to close it up and then about the same time or maybe even earlier while
all that was going on another part of OSD, Assistant Secretary Ignatius,
he decided that 200 airplanes weren't enough to be worth buying anyway and
so then we had to show him that well, we could buy a lot more if the airplane
was a success as we expected it to be. We could buy a Q version and a COD
version. We could also buy a training version, early warning version and
so on. But that again took another two or three weeks while we made up new
viewgraphs and showed him what those airplanes might look like.
Eventually it all got
settled and we were about to sign the contract when DDR&E's latest innovation
to solve all of our acquisition problems came along, Milestone Contracting.
We had thought that we were running slightly ahead of their time requirement
that you put that feature into each and every new contract but unfortunately
we got caught again. The concept was simply one that in the OSD scheme of
affairs you had a lot of individual points during the contract that you were
supposed to achieve on schedule. If you did not achieve any of those milestones
the whole schedule was slipped correspondingly downstream. This was tough
particularly on a contract like we had with ceiling options and the contract
already running several years into the future, adding the business if you
miss one little milestone and slip the whole thing until you got around to
correcting that. It was just an impossible kind of a thing to ask of a contractor.
And grossly simplistic. It wouldn't solve any of the real problems we had.
Well, as I said, we thought
we had the thing licked and we worked over a weekend getting ready for the
final negotiation, signing and getting approvals when we were trapped again.
The Sunday paper reported a speech that DDR&E John Foster had given to
some industrial association in which he said that every contract from that
day forward would have milestone contracting provisions included. So we knew
pretty much that we had been had again. But we worked up a presentation to
show him why we didn't need it and went to one of the higher level conferences
in which I was included. We had everybody, all of the Navy secretaries and
most of the OSD secretaries from Packard on down. Mr. Packard was then DepSecDef.
Foster was there and the rest of his crew. As I said the Navy secretaries,
OP-05, the commander of the Systems Command and then a few of us working
characters.
I was giving the presentation
which we had structured to try to show the difference between what other
people had done, and why we didn't need the milestone contracting. We already
had tight engineering control, tight schedule control and could change things
when we needed to change them. Mr. Packard interrupted me at about the third
chart and said in very stern tones, "We're not here to discuss whether
we're going to have it, we're here to discuss how we're going to
have it." Well, needless to say I blew my stack. I was really upset. Eventually
Adm. Baughman who had replaced Pete Elliot as the program manager took over
and did our backup presentation on how the hell we do milestone contracting
if they were to put a gun to our heads.
Incidentally I'd lost
all respect for Packard and the rest of those people over there. With episodes
like this and their complete lack of understanding of the acquisition process
in the working world, at least in the aircraft industry, as opposed to their
theoretical world. We'd held out high hopes for Packard when he first appeared.
This is another aside.
When he was being considered for the DepSecDef job, it had not been announced
yet, we were asked to give him a presentation on the F-14 and it was all
done with great secrecy. We weren't really sure for whom we were working
up a status presentation. We met with Mr. Packard in NAVAIR's board room..
Capt. Mike Ames, the F-14 program manager, gave him a presentation on the
F-14. It was a good presentation, showed him where we were, why we were doing
what we were doing and so on. When we got through he said, "Well, you guys
seem to know what you're doing. I'll leave you alone. Call me if you need
me." And we thought, God, this is the first Deputy Secretary of Defense in
years that has recognized what he knows and what he doesn't know. But it
wasn't long before he stopped leaving us alone to do our jobs.
We ended up in the S-3
by minimizing the number of milestones. For example, we put in on the R&D
lot only "integration of a complete ASW system" in a bench run, not saying
how well it performed, "first flight" of the airplane. First flights and
bench runs of an integrated system can be done with a fair degree of being
able to predict when you're going to be able to do it. You could do a first
flight just as a liftoff if you had to. I imagine if he had known more he
would have made us do more. Lockheed charged us a few million dollars for
putting the milestone provisions in the contract and we lost another month
or so. And it served absolutely no purpose.
On the whole the S-3 then
turned out to be a good program. We had some flying quality problems basically
because the airplane in order to meet the long time endurance requirement
had to have a lot of span and then it had too little drag in the landing approach
condition. That was probably the major flying quality problem then, getting
enough drag on the airplane so it would get down on the deck.
Then, ironically, of all
those modified airplane versions which we'd been forced to show before we
were allowed to proceed, none were approved. OSD forced the Navy to accept
inferior solutions to both tanker and COD mods.
Looking back at the time
the requirements were started it would have been easier to do a COD version
of the airplane for example if we'd had a little more space in the original
airplane. When the requirements were established, however, we still had
the CVS class carriers with older and less powerful catapult and arresting
gear. By the time we actually got the airplane in service of course the CVSs
were long gone. Well enough for the S-3 program. I believe Lockheed delivered
the 200 aircraft called for in the contract under the fixed price ceilings
specified. A successful program in my mind despite OSD.
After all my deferrals,
not willing to get started talking on the F-111B and then the transition
into the F-14 it's probably time to get onto that. As everyone must recognize
that's a big subject and that's one that took a good deal of our time and
effort over a ten year time period. The whole story probably needs to be
said in some kind of perspective and to do that rather than trying to talk
the whole story again I think we should insert in the record here a memo
that I wrote in 1980 that came about when Grumman and the Navy were being
sued by the descendants of a Navy pilot who was killed in an F-14 crash at
Oceana. I was asked to assist the lawyers that were handling the defense
side of the case. Basically the suit claimed negligence on the part of the
Navy and the contractor. There was some question about whether the Navy could
be sued or whatnot. But I had been asked by the Navy people to get involved
with these people. I think it was all a gratis kind of an operation. Anyway,
the law firm of course didn't have any background at all on the F-14 and
to understand some of the things that were going on they asked me to give
them a brief history. So this memo that I wrote which I'll identify as
Exhibit VF-1
is really an education for a lawyer. It's written in nontechnical terms
but it can give everyone a general picture of what went on from the mid-fifties
up to the time we finally got the F-14 under contract.
In addition to that story
I probably ought to mention that there's all kinds of data already available
on individual parts of the program. The McClellan Committee hearings, first
and second sets, and their final report is probably one of the better sources.
The final report was a good one. It was written by Charlie Cromswell, an
ex-Navy aerodynamicist who went to work for the McClellan Committee during
the second set of hearings. The first set of hearings were not officially
concluded but were just adjourned when President Kennedy was killed. They
were put off for a year or two before the committee went back and finished
up with the second set and wrote one final report on the whole thing. Officially
this was done by the Government Operations Committee, chaired by Sen. McClellan
and usually referred to as the McClellan Committee Hearings. In addition
to that there have been several books written on the subject of TFX/F-111,
but I have found none that come close to presenting the history of the program
as I saw it.
The TFX Decision
by Robert Ort came along in 1968 and that seemed to say that the whole problem
was the services not wanting to go along with civilian control and so on.
Just plain malarkey. Some of his facts are right but all the conclusions
are wrong as are reasons for the actions of the services. In Mollenhoff's
book Despoilers of Democracy he has a couple of chapters on both
the X-22 program reversal and the reversal of the TFX decisions. Those are
pretty good. He has a few facts in there that I didn't know about until I
read the book, well after the incidents that happened. He blames Gilpatric
and Korth. It says that Korth was forced to resign. I thought he just resigned.
That's probably a matter of opinion. Korth, to me, at least at the beginning,
seemed to be an innocent bystander.
One of the fancier books,
it was probably written as a Ph.D. thesis was something called Illusions
of Choice by Robert Coulam in 1977. He does not identify all the people
that he talked to but groups them as government employees or whatnot. Some
people thought I had talked to him but I had not. In fact none of the book
writers had ever talked to me and I thought probably I had more facts than
any other one individual in the whole situation simply because I had been
involved longer than anyone else. And I understand that there were theses
written for the Armed Forces College and so on and so forth. If a person
wanted to do research they undoubtedly could come up with file cases full.
The last book I actually read dealing with at least parts of the problem was
one written by Cdr. Andy Kerr (Ret.) and published by the Naval Institute
in 1987. Kerr was a legal assistant to SecNav Korth and did his job well.
Unfortunately he did not have a full understanding of the TFX/F-111 acquisition
for the year or two before his involvement.
TAPE 13 of 16,
SIDE A
August 15 -18, 1990
I had marked a memo entitled
"Brief History and Background of the F-14" as Exhibit VF-1
of this particular project and I talked a little bit about the other data
that's available.
I guess now it's time
to get started on more of that history. Going back to the various time periods
involved the studies after the cancellation of Missileer and leading up to
the TFX-F-111 program . Almost all the work was done by Fred Gloeckler and
his research division. It was a group that did preliminary designs and cost
effectiveness analyses on airplanes. Also involved were naval officers in
OP-O5. These were strenuous times for them doing a multitude of various and
sundry tradeoff studies and trying to compromise between an Air Force TFX
and a Navy TFX.
A word of caution on the
business. Most of the preliminary design people whether in government or
in industry tend to be somewhat more optimistic than are the other parts
of the organization that are building and testing, being concerned with the
operational side of aircraft development. I guess this has always been true.
And part of the reason that the TFX got into so much trouble was so much
of the early USAF work had been based on NASA studies done by John Stack
and the high speed aero part of the Langley research organization. Many of
the designs when we finally got a look at them in detail, usually years later,
were much too optimistic. The cockpits were too small. The radar antennas
,when shown at all, were maybe a foot in diameter instead of two or three
feet in diameter. The preliminary design people tend to get results that
are a little more optimistic than they should be. You'll see references on
occasion to the fact that many of us believe that the so-called "Navy TFX"
designs were probably incapable of being built but they were much closer
to being realistic than were those of the Air Force or those of OSD.
Well, back to the subject
at hand. I think the easiest way to do this is to take a look at a whole
series of memos that I first put together for Adm. Moorer when he took over
as CNO in the late sixties. We were then involved in the start of the F-14
program. The TFX F-111B was still costing a lot of money and he wanted to
know if there wasn't a history of the program. Well as far as Gloeckler and
I knew (the meeting where this question was raised also included OP-05 Tom
Connolly, and probably COMNAVAIR and was held in Moorer's office) no real
history had been written. Adm. Moorer then asked that one be done and since
we didn't have time to write one I assembled for him a whole batch of memoranda
that had been written since the program was started which when read would
give him an idea of what had gone on.
Since the last dictation
on this very complex subject I had taken the opportunity to go back and read
some of the stuff that has been written by others on the subject and I'm
a little confused right now as to how best to approach this problem. I reviewed
the final report of the so-called McClellan Committee, actually called the
Committee on Government Operations of the Senate by the Permanent Subcommittee
on Investigations. The final report wasn't written until 1970 but it is an
excellent review of the whole situation. A fair amount of detail is missing
but all of the facts seem to be in there and if anyone is really interested
in the subject they should go back and get at least the final report. If
they ever start reading the hearing reports they will find it so interesting
that they will probably get hooked and have to read for a couple of days.
Perhaps I'll stick in
a couple of these things that I originally talked about that we included
for Adm. Moorer. The first one I think we probably should talk about it is
a memo that I wrote in early '65, this is four years now after the beginning
of the program, but it's called "Review of Project Initiation," and is identified
further as Exhibit VF-2
. The reason for writing it basically was to get on the record what appeared
to be, to me, that some of the information used in that early decision was
wrong. The decision maker if he actually used any of those facts presented
by the committees that reported to him could easily have made a big mistake.
Unfortunately, all the stuff was held very closely early on and most of us
that finally got involved had never seen most of the early studies.
In this "Review of Project
Initiation" I point out that I came across in trying to find out how this
all started a Project 34 report. Project 34 as I was told was just one of
sixty or seventy projects that McNamara assigned or got started when he took
office at the beginning of 1961. I'm not sure that all the other were as
bad as Project 34 was but I wouldn't be surprised. Project 34 ended
up like many of these things. DDR&E ran it and working groups were established
and so on and so forth. The facts in the memo that are really important in
the long run were the facts that you can see that the Navy made a sincere
effort to try to compromise, to reach the goal that McNamara wanted. The
Air Force did no compromise of their position on the things that caused all
the trouble. In addition to that the real item that drove McNamara and all
through the years was his claim of a billion dollar saving.
This memorandum that I
wrote in February of '65 gives some of the data from that Project 34 report
which shows that the data used by the Air Force and the Navy on costing out
the programs were completely non-comparable. So I concluded from all this
that the decision makers had bum information but they probably would have
made the wrong decision anyway after seeing the way their thinking went.
In later years in making presentations I pointed out that the Air Force used
such a high learning curve "slope" that when their bigger and heavier airplane
bottomed out at the end of their production run it was down to where it cost
only about half as much as the lighter weight Navy airplane. This is obviously
ridiculous. If instead of compromising on an airplane that costs somewhere
in between the two, as OSD finally did to get their billion dollar saving,
if they'd told us to build nothing but the big heavy Air Force airplane they
could have claimed a cost saving of $2 billion. This may be hard for everybody
to understand but if you look at the curve sheets you can see it very clearly.
Years after the "Project
Initiation" memo, I made a set of three charts summarizing the "Air Force",
"Navy", and "DOD" estimates of aircraft weight, performance and cost during
that year of 1961. These may be easier to read than the ones in the basic
memorandum, and I'll include them as Exhibit VF-2
.
The next memo that we
ought to talk about is one that I wrote after the conclusion of the source
selection process and after the announcement was made in November of '62
that the winner was General Dynamics. The memo says that it was written primarily
for the record. Anyway, I wrote it as an internal memo from myself to our
assistant chief, then Adm. Fawkes. It was intended to be given to everybody
that was going to get involved in the hearings that had been announced by
Sen. McClellan so that we'd all be on the same team as far as our recollections
of what had been going on for the last year or so. This memorandum is identified
as Exhibit VF-3
.
The TFX history is complex
and one may not really understand the magnitude of the task that was given
to us. In a normal airplane development the Navy normally planned to spend
perhaps three months writing specifications for the airplane, for the proposal
data that had to be submitted, for the flight test program that would follow
after the development and so on. In this case we were told on a joint program
by the Secretary of Defense that we had two weeks to prepare the specifications
and one month total to get out the RFP. This could only have been done by
people that didn't understand the whole process. I think everyone at the
working level who was involved was just utterly aghast at the time schedule
that we had been given. Also bear in mind that all this was done with the
working level divisions within the bureau really not having participated
to any degree in this program. So they really were starting from scratch
in each division writing their own requirements for their specifications
and so on. Also of no help was the fact that the requirements were all going
to be put into an Air Force "work statement" instead of our normal specification
program.
One of the interesting
things that happened to me during the period was two or three days before
the 1 October 1961 deadline for the RFP to go out I got a phone call from
Adm. Pirie, then OP-O5, and he asked me to go to a meeting in the Pentagon
which was scheduled as I recall sometime that late morning. I found out later
that the reason I was selected to go was that DDR&E had called for the
meeting, but did not want any military people to attend. The Air Force representation
came from the secretariat level in the Air Force. The R&D secretary attended
the meeting. A lot of DDR&E people were there. Our R&D Secretary
Wakelin was out of town and they couldn't find another civilian more qualified,
so I got selected to go to the meeting.
When I got to the meeting
I found out that we were supposed to approve the work statement. Well I checked,
of the people that were there I was the only one that had seen the work statement
so I suggested that perhaps we had better postpone the meeting until the
others had a chance to look at it. This was done and the meeting reconvened
at something like seven o'clock that evening in the Pentagon. Dr. Brown was
supposed to chair the meeting and he was twenty to thirty minutes late in
getting there. He walked in followed by a half dozen of his staff and so
on. His first words were after looking around the room and seeing no military
uniforms, "Well, what have they done to us now." He was obviously
referring to the military. Those were the first words I had ever heard from
Dr. Brown directly and it didn't enhance my opinion of him at that time.
My opinion really hasn't changed over the years that he might have been a
fine nuclear physicist but he sure didn't know airplanes, nor the aircraft
acquisition process.
In rereading this memo
(Exhibit VF-3)
now it seems clear that I could have written one two or three times as long.
We failed to detail all the problems that we had in working with the Air
Force. Among other things they had insisted on a page limit for the proposal.
As I recall they allowed something like 300 pages for their basic proposal
and some 500 pages of backup material. In our system of running design competitions
we had never limited the number of pages for a variety of reasons, all of
them in my opinion very sound and practical. In this case there were requirements
written for the data to be submitted. The data to be submitted took far more
than the 300 page limit. There was no way a contractor could comply with
the limit and still meet his data requirements. The fact that the whole thing
was secret was also a real headache.
As one can undoubtedly
gather from the tone of the writing in my memorandum the Navy was greatly
disturbed by the quality of the Air Force's evaluation, results, effort,
whatnot. There's no doubt that we were truly surprised. After some reflection
on what had happened because we knew that the Air Force had plenty of well
qualified engineers in all areas, they undoubtedly had probably twice as
many as we did and yet they were not able to do a decent job on the TFX evaluation
effort. I believe the fault lay with their organization. At one time the
Air Force had basically a functional organization. There was an aircraft
lab, a powerplant lab and so on in which the engineers in a given discipline
worked together in a single group, pretty much the way we in the Navy were
organized.
In one of their management
reorganizations the Air Force adopted the SPO concept, the System Project
Office, which was a true vertical organization. The thing that happens in
the real world is that the first SPO that comes along picks off the best weight
engineer, the best aero man, the best powerplant man, the best ejection seat
man and so on. When the next program comes along they take the second best,
etc. By the time the F-111 program got set up it was probably the eighth
or ninth of the SPOs with the result that those assigned to that program
were really the lesser lights of the Air Force organization. Some of us had
known a few of the engineers involved but most of them were young and inexperienced.
For a specific example in the weight area where we had depended upon the
Air Force to do the first weight analysis we were told later that the only
weight man they had on the program was a GS-9 individual who had little or
no experience in weight estimating, having been used in other aspects of
weight and balance control prior to his assignment to the F-111 SPO. Although
he worked hard, he just didn't have the experience to do the job. The weights
came to us two weeks late and seemed so questionable we were forced to do
a real quick analysis of our own which was rough by our standards. We were
quite disappointed.
Another thing I ought
to mention when you read this memorandum is it refers to the SSB, the Source
Selection Board. In today's nomenclature that is the Source Selection Advisory
Council. It was a relatively small board of one member each from the various
commands, TAC command, Systems command, Logistics command, and the Navy member
was Adm. Ashworth, our R&D admiral and my boss.
At the time I wrote this
memo as you can see on page five I had said that the decision to recommend
Boeing went through the whole military system, but I later found out that
was not correct. When it got to the level of Gen. LeMay who was the commanding
general of the Air Force at the time, he recommended that two contractors
be continued in the competition and Adm. Anderson went along with his decision.
During that first round then they ended up -- the final decision makers going
to the secretary recommended both Boeing and General Dynamics. There was
no feedback provided to the SSB, Adm. Ashworth, or our working level.
After the first round
of the competition was over and we had eliminated four of the proposals,
we were really unhappy with the designs. We got direction basically from
the Secretary of the Air Force and approved by some higher authority in OSD
to go ahead and do a second competition, try to get some satisfactory proposals
that would meet the requirements. Well obviously the contractors were told
they had "deficiencies" the first time around. By that time the Air Force
had run their engine competition and decided that the GE engine was really
not going to be ready in time. It was a paper engine, wasn't even under contract.
It should never have been included in the list of engines that could be used.
However, without it, the task of the contractors to propose designs meeting
all the requirements was made even more impossible. Both contractors had
deficiencies to be corrected. The Navy told the contractors the way we had
checked all the performance items. In the case of the Air Force, however,
they really didn't tell the contractors the answers, but just told that they
had a "problem" with a cost or with the mission requirements, or whatever.
It doesn't help a contractor very much to say you've got a "problem" without
telling him what it is.
So when the second round
came in things were a good deal worse than they were before. This then was
reported up the line of course all through the Washington briefings. Again
we recommended that we stop the program, go back to having a Navy airplane
and an Air Force airplane with each running our own development. This recommendation
obviously was not accepted.
The SecDef and so on told
us to go ahead with the third round and this was a very short one. We were
told to report back and tell them what the differences had to be between
the Air Force and Navy versions in order to get satisfactory airplanes for
each. Neither contractor was really given enough time to do the job and the
stuff that came back from General Dynamics showed it was similar to a two
or three week effort as you might expect. However, Boeing came in with a
brand new proposal, a great deal better airplane for the Navy. We would have
been real happy to go along with that. Our problem however was the Air Force
in their evaluation of the third round proposal ended up by saying that the
radius requirement which was supposed to be that 200 miles dash distance
was better than it was in the first submission. This seemed to us to be obviously
impossible. The Boeing proposal had put on 15% more wing and there was no
way that the low-low-high mission was going to get better. The Air Force
checked it at 185 miles which was close enough to the 200 that they really
didn't make a point with the contractor that this was a deficiency. We knew
that eventually the Air Force was going to find out that it wasn't going
to go that far and that they would then get us into a mess by immediately
making changes in the design such as adding more fuel, that made the Air
Force airplane better but made our airplane worse.
The other thing that happened
during that third round was that in the cost proposal the Air Force in their
evaluation system had used "cost standards" which were not told to the contractors.
It was the Air Force estimate for a generic type of TFX airplane basically.
The way the point system was set up , the higher or the closer the contractor's
cost proposal came to the Air Force estimate, the more points it got in the
point rating system. The contractors were both bidding well under the cost
standards and again the Air Force told them that they had a problem with
the cost estimates, but they didn't say whether they were high or low. If
I had been a contractor I would have done exactly what the contractors did.
Each time they bid they bid a little lower than they did before which basically
increased the problem. These kind of problems all through that year or so
that we fooled around with these evaluations almost drove us crazy. It was
very difficult dealing with a group of people whose rationale you never understood.
I might also mention at
the briefing given the contractors for that third round, Capt. Shepherd,
the Navy assistant to the SPO program manager, in his talk about what was
going to happen said that the third round was to define the differences between
Air Force and Navy models, and his advice was, "Let the chips of commonality
fall where they may." In other words, get the airplane for the Navy that
was satisfactory and get one for the Air Force that would meet their requirements.
If they were different, so be it, but define the differences.
When we finally received
the fourth round of proposals the Navy's design from Boeing was the same
as that which had been submitted in the third round and was definitely a
pretty decent airplane. We under the circumstances were willing to accept
it. It was bigger and heavier than we wanted but it looked like that was
the only kind of an airplane we were going to be able to get, and we needed
something to get out in the fleet to replace F-4s. At the time our plan was
that we, the Navy, did not want to make a decision on the total program on
who was going to get the contract because we honestly thought the program
was going to be a failure and that if the Navy made the contractor selection
we would get blamed for the program failure and we didn't want that to happen.
We wanted to get the airplane that would do our job but we wanted the Air
Force to make the decision. Fortunately, the Air Force officers from the
Tactical Air Command who were rating the operational portion of the competition
in the Air Force's scheme of things were all in agreement with us, that the
Boeing design was much better. We thought we had probably achieved our goals
of letting the Air Force take credit for the selection decision. After all,
they had responsibility for management of the program.
Unfortunately, I guess
in retrospect, we said that we had no significant preference between the
two which was not really true. We had a significant preference. Those words
came back to haunt us, particularly me, many times over. It was a mistake.
"No significant preference" showed up in the evaluation board recommendations
to the Air Force and went into the Air Force's final write-up. The Navy voting
member on the Source Selection Board or what would now be called the Advisory
Council had been very direct, this was Adm. Ashworth. I might also comment
at this time that Adm. Ashworth and I guess Whitey Feightner, the fighter
project officer at the time, myself, and the other Navy people that were
involved all knew what each other was doing.
Adm. Ashworth had been
briefed on what our evaluation was. We talked completely openly and he told
us he would take no action that we wouldn't agree with and of course he did
exactly that. He acted properly and with a great deal of intelligence and
so on. We had not known Adm. Ashworth long, he'd only been there a short
time replacing Adm. Fawkes. He ended up by being one of our favorite admirals,
that is the easiest way to say it.
I guess I can also mention
a bit about the last paragraph where we said that the Navy method of letting
everybody know what we were doing and discussing it openly seemed to us to
make a lot more sense than the way that the Air Force operated as will come
out later in some of this history. Might as well describe it now I suppose.
The Air Force Evaluation Board reported their results to the Source Selection
Board. After their evaluation results were presented they withdrew. They
were not aware of what the decision of the Source Selection Board was and
yet they continued to do the same briefing all the way up the chain of command
first through the "Using" Command, and the System Command, the Logistic Command
and so on up to the chief of staff and finally to the secretary. All the
time the briefers were not aware what the decision was. They talked in their
peculiar code language, giving everybody a letter like contractor X and contractor
Y. The actual decisions were in a very brief decision paper from each level
from the Source Selection Board through the using commands to the chief of
staff, were carried in an "Eyes Only" envelope. The message could be as brief
as "The Source Selection Board recommends contractor X." A second and separate
message contained the identity code, "Contractor X is ____." I thought then
and now that the secrecy restrictions were grossly overdone, and probably
contributed to the selection reversal. I'm still not convinced that when
the secretaries got their briefing whether they knew or not what the Source
Selection Board had recommended. Today the written record all looks like
they knew but I'm not sure that they did. When they did the briefing I think
the envelope was delivered to Secretary Zukert in the conference room. I
was sitting on the sidelines and I didn't see him read it.
The other thing I might
mention is that the Air Force held their whole procedure secret, not only
what they were doing in it but the actual procedure itself and later on when
the McClellan investigation committee got into the act the Air Force made
the committee agree that they would not disclose some of the aspects of the
way they did their business. Why that should have been secret I have no idea.
Well, as everybody knows
now the decisions through that round were all unanimous by the military that
Boeing was the winner, that we recommended Boeing be given the contract and
the results were presented to the secretarial level during a morning session.
In the afternoon they briefed Harold Brown who had been unable to attend
the morning one. He didn't make any real comments other than to show his enthusiasm
for Air Force's ferry mission requirement.
TAPE 13 of 16,
SIDE B
That mission as described
in the proposal had the airplane taking off from an east coast base, landing
in North Africa somewhere, and apparently after a refueling, the pilot was
given his strike coordinates and sent off on a bombing mission. Presumably
he'd carried the bomb along with him. Dr. Brown thought it was a great capability.
Most of the operational people there were not quite as enthusiastic.
The full evaluation was
not briefed to McNamara. As I understand it, McNamara decided that he only
had time for a partial briefing and Col. Charlie Gayle, the SPO program manager,
and Capt. Shepherd, our Navy assistant, took perhaps fifteen or twenty viewgraphs
and gave McNamara a very short briefing. They reported back to us, or Shep
did, eventually that there was no real discussion at the time and there was
no way for us to know what in the world it was that the actual briefing contained.
We know darn well that it didn't contain the recommendations of the Source
Selection Board because Col. Gayle, the program manager, wasn't privy to
it. He was only at the evaluation board level so he couldn't focus the presentation
on what should have been the advantages of the Boeing design over the General
Dynamics design. When you're talking to the secretarial level you better
sure not let him be faced with facts that the raw point score was very close,
perhaps 672 to 670 or you know very well he can make the wrong decision.
And that might well have been the thing that caused all of the problems. In
any event, the services got overruled and General Dynamics was announced
as a winner, I think on the 24th of November. From that point on then the
Air Force started on the paperwork leading to a contract. Boeing was unhappy
obviously. The trade journals all talked about the overturn of the decision.
Senator Jackson of Boeing's
home state requested the Government Operations Committee, chaired by McClellan,
to investigate the award to make sure that the government was going to buy
the best airplane at the best price , which we obviously believed was not
being done. The timing was such that by the time the committee got around
to announcing that a full investigation was being initiated, it was the day
that the contract was to be signed. The record shows that McClellan called
DepSecDef Gilpatric and requested that the contract not be signed. At the
same time the senator had written a letter requesting this, and had it hand-carried
to the Pentagon. Gilpatric, for what he claimed later were the best interests
of the country, told the Air Force to go ahead. So the Air Force went ahead
and signed the contract at Wright Field. The contracting officer got questioned
by the McClellan Committee investigators later and he knew nothing about
the request from the Congress to not sign the contract.
In late December, just
before Christmas sometime perhaps the 21st, the contract was signed, and
the McClellan Committee announced that they were going to have an investigation.
The investigation was really not very well done. The McClellan Committee's
most recent investigation I guess had been of the Costa Nostra, a mafia racketeering
type of thing. Their staff was equipped to handle that type of subject but
none of them were experienced in national defense issues. McClellan obviously
was. He was on the appropriations committee as well and of the other senators
who were involved, some were well informed and others were not. But the staff
initially was in very sad shape to do this kind of an investigation.
Well that Source Selection
memo -- my timing on writing it might well have been because of the fact
that investigation was coming up and I really thought that everybody on our
side of the thing should have the same facts and refresh everybody's memory
as to what had happened in the last year and a half. As soon as the investigation
was announced the legal counsels and so on and so forth tried to get informed
on what was going on. I remember going over to the Navy counsel's office
in the Main Navy Building. At that time we were in the W Building which was
back of Munitions, one of the temporary buildings put up during World War
II. It was a two block walk to get over to the chief counsel's office of
the Navy. The chief counsel looked over the Source Selection Board record.
I had a little folder, my memorandum and I had copies of the recommendations
of the boards and so on through all four of these rounds of evaluation and
so on. He said, "Oh, my God, we've really got a mess on our hands." There
was no question but that he recognized the problem immediately.
The reaction however of
the Secretary of the Navy was anything but that. I remember getting a call
from Cdr. Andy Kerr, Korth's legal counsel, and Kerr wanted to know what
the defense was for Korth and I said there wasn't any defense. Well, we ended
up in a meeting in Korth's office I think the day before he was to be asked
questions by the staff investigators. We had the usual group, the Chief of
the Bureau, OP-O5 and so on, program manager, Adm. Ashworth was there, probably
eight or nine of us.
Secretary Korth told us
directly that he really had very little to do with the decision. He admitted
that he didn't understand all the factors anyway. The whole program was supposed
to be under Air Force management. He said that they had shoved a document
at him finally and he had signed it in the place where it said SecNav. Then
he asked the group what should he say to the investigators. When no one else
answered the question, I made a recommendation to him and the group to tell
them exactly what he had just told us, that he had nothing to do with it,
that the Air Force had made the decision and go talk to SecAF Zukert rather
than talking to him. His words were, "Oh, I couldn't do that. This is all
part of the secretariat," or something of that nature. From that point on
he was in deep trouble and he got in worse and worse. Andy Kerr, the legal
aide did a superb job of acting as defense counsel but in doing so he got
crossways with all the rest of the Navy because he essentially came to be
on the side of OSD while the rest of us were anywhere but on that side. I
think Kerr made a mistake. Korth should have taken our advice and he would
have been a lot better off. As people probably know he got accused of conflicts
of interest because of his banking connections in Texas and he was actually
forced to resign. Whether he deserved that or not I have no way of knowing.
Cdr. Kerr later did not get selected for captain and retired from the service.
From that point on we
really had a juggling act on our hands. We were trying to get a new airplane
started and at the same time the McClellan Committee hearings started on
the 26th of February. When McClellan started those he announced in the first
hearing what the ground rules would be and so on. They would call witnesses.
Witnesses would be under oath. The services were allowed to have two representatives,
the wording was "two representatives and not more than three from the Navy."
The Air Force and SecDef also were to have "two and not more than three people"
that could sit in. Both Boeing and General Dynamics were allowed to have
two witnesses sitting in all the time and McClellan announced that he expected
the hearings to last five or six days. What actually happened was hearings
went on fairly expeditiously at the beginning and then they got spaced out
for a way, and went on until sometime in November. Then President Kennedy
got shot and the hearings just stopped. They wrote no report, reached no
conclusions. The hearing record was out in book form but the committee didn't
make their report.
I guess I also should
mention that the hearings, FIRST SERIES they ended up calling it, were all
classified, closed sessions. The public wasn't allowed in as you could gather
from that, only two people from each of the services. In any event they ended
up with something like 2700 pages of testimony, really not a well conducted
hearing in my opinion. The fact that the hearings were closed and
much of the data was classified either confidential or secret created real
workload problems for many of us. When the hearings were on there had to
be a security review committee that would go over the transcripts as they
were issued and delete the classified material. Somehow or another I ended
up on that too along with Cdr. John Hill who was then in OP-506. In some
cases I would testify in the morning and then sit in the Pentagon that night
going over testimony and deleting the classified material. The days got awfully
long at the time.
The other thing that was
peculiar about the whole thing was if I had been McNamara I would have told
everybody to shut up and say as little as possible. But McNamara issued a
directive to both the Air Force and Navy and said cooperate to the fullest
degree. Well obviously we cooperated to the fullest degree. Every time we
cooperated we got SecDef into more trouble which then annoyed him to no end.
He had elected at the beginning of the hearing to have the services present
their position and then he was going to come in on that fifth or sixth day
and clear up all the confusion and expected to wind up with a laurel wreath
I guess.
What really happened of
course was that the first day they called Mr. John Stack who had been the
high speed aerodynamics expert at Langley who had cooperated with the Air
Force and worked on the early Air Force program with Gen. Everest and Gen.
Momyer that were pushing the low altitude supersonic mission for the Air
Force. By that time Stack had resigned from the government and was actually
just going to work for Republic which had been one of the competitors in
the competition by the way. I thought it strange to start with Stack, but
as I learned later, they thought he would take thirty or forty minutes but
he took the whole first day. From then on it went like that.
Since the Navy had been
told to cooperate we cooperated. There were many nights that we spent with
Capt. Ike Kidd, then Adm. Anderson's aide, providing comments, questions,
going over data and whatnot at the request of the committee. There was a
great deal of work. At the same time we were trying to go ahead with the airplane.
They were tough days.
Much of the early maneuvering
of the committee concerned a mistake they had found in the way the point
scores were tabulated because the Air Force had mentioned that the point
scores, the raw scores and the weighted scores and all that jazz had included
the AMCS fire control system for the Navy to be part of the Air Force point
score system. I'm not really sure why they did that, but they did, and when
the final scores were tabulated they forgot to weight the scores for the
AMCS. The weighting system had been approved officially by the Source Selection
Board. (In reality it was devised by an ad hoc committee of the Air Force.)
Anyway, when the AMCS score was weighted it changed the totals from General
Dynamics being a few points ahead to Boeing being a few points ahead. The
committee apparently expected that to be a real shocker and McNamara would
immediately say he made a mistake and picked the wrong contractor. Unfortunately,
of course, the point score by itself had little to do with the decision and
the Air Force finally testified that they used point scores to aid in the
evaluation but not to be a decisive factor. It would have been a lot easier
for everyone if they never had used a numerical scoring system. I mentioned
the standards before and the cost standard was one that you got the most
points by being closest to the Air Force standard which was higher than the
bid so the higher the bid the higher, within reason, the point score you
got. Sure enough GD which had bid higher -- perhaps $50 million, maybe more,
than Boeing -- got a better point score in the cost area because they were
more expensive which of course was contrary to the way we did business. There
are so many things that just defied the imagination during that whole episode.
Rationally I couldn't figure them out anyway.
Well, a month later the
McClellan Committee got to the Source Selection Board itself and they testified.
The early witnesses like myself and the people that had been on the evaluation
board, the program manager, and so on had all been told we could not write
statements to present to the committee. So then we had to depend upon the
committee to ask the right questions to develop the facts and they seldom
did. Most of the committee was opposed to McNamara and company but he had
a couple of defenders on the committee, Muskie of Maine was a McNamara supporter
as well as Javits of New York, although Javits was seldom there. Muskie was
there most of the time.
When I finally was called
they were still going through commonality and point counts and whatnot and
whatnot. I finally lost my cool or something and said something that the
commonality issue was all poppycock, that what you're really interested in
was getting the best airplane at the lowest price. It didn't make any sense
to award a contract because one guy had 72% commonality and the other one
had 56% or 70% or whatever it was. Part count commonality has no real bearing.
It obviously is only a means to reduce the cost of a program so you should
really be doing your decision making on the basis of cost not on commonality
count. But that argument went on for years.
In any event we went through
the hearings. They were at the point where Zukert had been on the stand for
I think seven or eight days, the longest period of any witness. He seemed
proud of the fact -- had a sign on his desk proclaiming his record. They
had already heard Korth and Gilpatric, then Kennedy got shot and the whole
thing recessed. They didn't restart the hearings for three years, in 1966.
They ran the second series then with 678 pages of documentation. Those were
open hearings. The censorship stuff on security matters had disappeared.
By that time the subject matter was unclassified or largely so, so we didn't
have that working level security review committee which reduced our workload
a bit.
The final report was written
just before Christmas in 1970 seven years after the start of the hearings.
Anyone who wants to get a good history of the whole program and what the
big decision items were is well advised to read that report. It was entitled,
"TFX Contract Investigation, Report of the Committee on Government Operations,
U.S. Senate, made by the Permanent Subcommittee on Investigations. Report
No. 91-1496. 91st Congress," and dated December 18, 1970. One of the reasons
the report is so well done it was written by an engineer instead of the lawyers
that had been on the staff when the thing started
I guess that's an interesting
story, too. Sometime about when the second set of hearings started I got
a call from the committee and wanted to know if I knew Charlie Cromwell.
I said, yeah, I knew Cromwell, he had been an aerodynamics engineer with the
Navy, a flying qualities man, good engineer, but he had resigned from his
job and set up his own business as a tree surgeon. That didn't go well because
of the labor situation. He couldn't get people that he could depend upon,
Charlie said later. So he applied for a job up on the Hill and got to the
McClellan Committee. McClellan Committee looked into his background and hired
him. From that time forward the committee investigation made a heck of a
lot more sense and the final report, as I've said, is very well done and
I recommend it to anybody that's really doing research on this whole program.
I probably ought to get
back to the development part of the game. Within perhaps two or three months
after the program was under contract, the Air Force, as we had predicted,
found out that the airplane didn't go far enough for them so they suddenly
announced to the Navy that the airplane had been lengthened, their version
had more fuel in it and the structural weight was going up. The increase
was marked for them, something like 10,000 pounds as I recall. This sent
off great shockwaves with us. I remember Adm. Schoech called a conference
and we all met in the board room with lots of people from General Dynamics
and from the Air Force. Adm. Schoech pointed out that life couldn't go on
that way, that this was a joint program and we could not tolerate those kind
of weight increases. It was actually that which we had anticipated would happen
and it did. The weight increases went on anyway. The Air Force really couldn't
back off. The airplane as it turned out was short legged anyway, they had
no choice but to put in more fuel. I guess that must have been in 1963 and
the program went along with weight status reports coming into us on a monthly
basis. On the Navy airplane, the weight had been going up and it was up by
perhaps 1,000 pounds when suddenly we found out that the weight was really
up by a great deal more than that. We sent our senior weight engineers, Keith
Dentel and Ray Hook, down to Ft. Worth to look into it. It turned out that
the contractor, General Dynamics, had really been keeping two sets of books.
He reported a weight increase to us of 2,000 pounds all in one fell swoop
when it was actually 5,000 pounds. They had not reported 3,000 pounds on
the basis that there would be a weight reduction program that would get rid
of it. Well, with any kind of a weight increase of that magnitude of course
we were in deep trouble.
In February of '64 we
reported on a complete reevaluation of the F-111B airplane in
Exhibit VF-4
. I won't go and describe all the things that happened at that point. We really
wanted to cancel the airplane but politically we couldn't do that. We recommended
that General Dynamics stop work and redesign the Navy airplane. An eminently
sensible position which was not accepted at higher levels.
The more I think about
this the more things I remember that someone might be interested in about
the peculiar things that happened during the period that the hearings were
going on. I can remember being in Adm. Anderson's office with Whitey Feightner
and we had been bringing him up to date on the whole TFX happenings that
were going on and the investigation which was then starting. I remember Adm.
Anderson saying to both Whitey and myself, "If anything ever happens to you
two from a career standpoint let me know, I've got enough data in my file
cabinet that will blow the top off this building." Kind of strange. I had
never given any consideration to any vindictive personnel actions up to that
point in time.
It was a little surprising
then that Adm. Anderson himself shortly after he testified that Boeing was
a better airplane in the competition ended his naval career by being forced
to resign and given a job as ambassador to Portugal. I think for the record
he claimed that he had not been fired but I don't think any of us were really
convinced of that. And then at the same time Adm. Ashworth suddenly got orders
to go to the Med and head the Sixth Fleet. I can remember the counsel of
the McClellan Committee telephoned me as well as some of the naval officers
and questioned us on the transfer of Ashworth. I was told by the committee
that if I ever heard anything that was being done to Ashworth to keep him
from progressing in the Navy to let them know. Well, you couldn't really
complain at that time. Ashworth didn't complain to me about getting the Sixth
Fleet, but he never returned to Washington duty and after that tour he also
retired. Now that I think about it, though, it does seem strange that so
many officers connected with the F-111B/F-14 programs retired immediately
or after a single tour out of Washington, and none were promoted. Anderson,
Ashworth, Schoech, Rees, Ames, Shepherd come to mind immediately. Vindictiveness?
I recall another episode
affecting me personally. I guess it was probably during the first evaluation
period. Our aero people telephoned me and told me that they couldn't find
the dimension for the flap chord on the General Dynamics design. Well, I
didn't think twice about it. I just picked up the telephone and called the
local General Dynamics office, told them we couldn't find the flap chord
dimension, could they provide it for us. Within the day they came back and
told us what the dimension was. It was the type of thing that we did routinely
when we ran a competition. Within a few days though I found out that I was
on the pan. General Dynamics had notified the SPO that the Navy had asked
for information and had made unauthorized contact with the contractor. Obviously,
I had not gone through the SPO, nor had I talked to the contracting officer
in Dayton. Apparently all of these were things that I should have done in
order to get the dimension of a flap chord so that we could calculate performance.
It just didn't make any sense but the Air Force actually sent a letter to
the Chief of the Bureau recommending that I be reprimanded, a letter go into
my file and so on and so forth. Adm. Hines was our deputy chief at the time
and he called me up, asked me what the hell I'd been doing now. I explained
the thing and he laughed and dismissed the whole thing. Whether something
ever went into the file I have no idea, never looked at my file. Maybe I
should.
One other strange deal
was I was working at home on a Saturday afternoon, writing up something on
the justification for what we were doing and I had a phone call from the
staff of the McClellan Committee. They requested that I come down and see
the senator that afternoon and so I said well, I'll have to check it out
with the Navy. They said okay, let us know or some such thing. So I immediately
telephoned the CNO's office. Ike Kidd had the duty that Saturday afternoon.
Ike said, "Okay they've requested that you go down there, you do it, and
I'll clear it with the Secretary of the Navy's office." It was at the time
in the program that the Secretary of Defense had gotten "itchy" and SecNav
was also, and there was lots of worry going on about who was doing what to
whom. Actions of this sort were unprecedented in my experience, which at
that time had been over twenty years in Washington and involvement in over
sixty new Navy aircraft.
But, I proceeded to go
down with my briefcase full of stuff to see Senator McClellan. I parked and
went into the Old Senate Office Building, got up to Senator McClellan's office
and the gal on the outside said, "Just a minute, Mr. Spangenberg," and I
waited outside. One of the staff guys came out and he said, "Something funny
is going on. You are to be told that you cannot see Senator McClellan." And
I said, "Oh, is that so? Okay." About that time Senator McClellan said that
he wanted to see me so I walked into the office and he was extremely angry.
His face was flushed and he said, "Mr. Spangenberg I've been told that you
cannot talk to me," and then he went on a diatribe about McNamara and the
things that he was doing to the country. Incidentally, in McClellan's office
that afternoon he had his whole Democratic staff and Republican staff people
on the committee and they were all waiting. I don't know what they were going
to ask me, I never did find out but anyway I listened to McClellan. McClellan
said he was going to "get" McNamara if it was the last thing he did. He had
lost a son or two during World War II and he was a very patriotic guy who
didn't like the kind of things that were going on.
Anyway, I left and started
home but thought I'd better check in with CNO which I did. It was now late
Saturday afternoon. I went down to Ike Kidd's office. Ike waved me in and
said, "Thank God you came in." He said, "Sit down and listen." He called
the yeoman and dictated a memo and went through the things that had happened.
Apparently after my telephone call to Kidd he called Capt. Spence Robbins,
our legislative liaison officer, but Robbins had already been called that
he should come down to the Pentagon for something. His wife didn't know what
was going on. Ike was a little perturbed and apparently called SecNav's office
and they were very upset, according to what Ike was dictating to the yeoman.
When it all happened Ike said that he was talking on one telephone to the
McClellan Committee and the other telephone to SecNav's office. He had told
them that he gave me permission to go down and they told him that he couldn't
do that and then SecNav's office apparently told the McClellan Committee
that I couldn't talk to them. Well, it was all a great mystery to me. I didn't
know what was going on. Kidd was angry and it was not apparent how anybody
could have done this unless somebody's telephone was tapped, either CNO's,
mine or Ike Kidd's or somebody's. To finish the tale -- early the following
week, a letter or memo arrived in my IN basket from SecNav advising me that
I should not talk to Sen. McClellan or his staff without permission from
SecNav's office. I had not been advised that the restriction was "in the
mail."
TAPE 14 of 16,
SIDE A
August 19 - 22, 1990
Now back to the F-111
development program. In a 5 February 1964 letter to the CNO a recommendation
was made that we stop the airplane until we could get a redesign that would
meet our requirements. Obviously that wasn't accepted by the secretaries
who eventually decided that we should go ahead, keep the weight improvement
programs going, and the contractors would be asked via the SPO to send in
some studies for a fall back design. The fall back designs then came in near
the end of July of that same year 1964 with a minimum of data. General Dynamics
showed us four designs which were all in the SWIP (superweight improvement
program) category. Grumman had a little more data on a design that they identified
as CWIP, the Colossal Weight Improvement Program. It had a completely new
fuselage and saved considerably more weight than the GD designs did. As accepted,
the decision in that case was to continue with only SWIP, the least costly,
hold the contractor to his schedule and to make some management improvements.
The latter turned out to be the assignment of an admiral (Bill Sweeney) to
Wright Field to become the deputy program manager. It really solved none
of the technical problems. Some more of that detail is in that letter of
14 August 1964 which I'll mark and put into the record as
Exhibit VF-5
.
Sometime either early
or later, I'm not quite sure which, there was a relatively formal fighter
study done in OPNAV. I guess it was entitled the "F-111B Requirement Study."
I wasn't involved to any great degree other than to provide weight and performance
data to the study people in OPNAV. Gloeckler was more involved as you would
expect. Adm. Zumwalt, then OP-096, headed up the study. Zumwalt was considered
a protege of Secretary Nitze and was probably influenced to be kind to the
F-111B. The requirement study I thought was a complete waste of time because
its conclusion was that the F-111B was worth buying assuming that it met
its requirements. The requirements hadn't changed since the first study which
had been done a year or two before, when the F-111B started. We had signed
off then that if it met the requirements it was an acceptable airplane to
put into the fleet and would do a useful job. By this time, however, we knew
that the F-111B was not going to meet the requirements, so telling us that
the airplane was satisfactory as long as it did just didn't make any sense.
The airplane continued
on its merry way with the secretarial level holding the schedule sacrosanct
but with the airplane gradually getting worse and worse , though they did
approve some changes in the design as we went along. The new high lift system
got designed and approved, an upgraded engine, the P-12 was scheduled to
go into the airplane, work on new inlets or changes to the old one and weight
reduction programs were continuing. The only problem with all of this was
that every time there was an improvement it got incorporated farther and
farther down the production line so it looked like we were never going to
get a representative airplane where we could prove with hard data, which
was a requirement being levied upon us, that the airplane wasn't going to
meet its requirements.
Well, obviously the airplane
never did and kept going down hill. Maybe as a side issue of this could be
of interest on the kind of problems we were running into at the time. Executive
management reviews, EMRs, were being held perhaps once a month where the
SPO reported to the secretarial level what the status of the airplane was
and so on. Included in those briefings were tabulations of weight and performance
as calculated by the contractor, the Air Force and the Navy. These always
showed up as the contractor being the most optimistic, the Navy being the
most pessimistic and the Air Force in the middle. Some kind of a committee,
ad hoc committee, got appointed to try to get some kind of an arrangement
worked out where the Navy and Air Force would get together beforehand and
show only one set of data. To do this we ended up by sending performance
estimators to Wright Field to reach agreement on the basic parameters, low
speed drag, high speed drag, thrust, etc. Similarly, the weight people had
gotten together and agreed on the basic figures which would be used. The
next EMR came along and the differences were there just as big as they had
ever been. We immediately got in touch with our opposite numbers in the Air
Force to find out what had happened. Their reply was that they were directed
not to give them their "best estimate" but rather to give them an "estimate
of the best" which might be achieved if you're optimistic enough. I guess
the issue of the differences between Navy and Air Force estimates on weight
and performance never was satisfied.
With the airplane getting
worse and worse and yet with apparently no real way to get the thing killed
a lot of studies were going on both in and out of the Navy on our options.
One of the concepts that came along was that we would accept the fact that
we were going to have to have one squadron of F-111Bs on board our carriers,
and they would be used for the FAD (Fleet Air Defense) mission only. Then
we were to find ways to get a reasonable capability for meeting the so-called
OFR (Other Fighter Requirements), fighter escort, close air support, etc.
Out of that acceptance
of reality came a concept of an airplane called VFAX. There were attempts
made to buy VFAX. It appeared in some of the Navy preliminary budgets but
never made its way all the way through. VFAX, as defined then, was an airplane
about the size of the F-4, in that same weight class, had a variable sweep
wing and the requirements were set out to be that the airplane would truly
match the capability of the F-4 as a fighter and the A-7 as an attack plane.
The cost effective studies then all showed that one squadron of F-111Bs and
three squadron of VFAX was better than buying two squadrons of F-111s and
continuing A-7s, or with two squadrons of F-111Bs and two of VFAX. That approach
of one squadron of F-111Bs and three of VFAX really was a Navy position then
as a way to solve the fighter problem for the better period of a year, a
year and a half I suppose.
A few years later a VFAX
showed up again in the development plans leading to the F-18. The terminology
of VFAX was used again but you should bear in mind that the original VFAX
was a very capable airplane and the later VFAX was marginal at best, being
somewhat less than the A-7 in its attack capability and really no better
than an F-4 as a fighter. In the cost effectiveness studies that were done
it was rated below an F-4 because the later VFAX was a single-place airplane,
while the original was a two-place airplane.
The 14 August letter which
summarizes the things that happened in the July 1964 submission I've labeled
as Exhibit VF-5
. Incidentally, all this period, these enclosures, the February and July
ones are covered in the second set of hearings of the McClellan committee.
As the years went by with
the F-111B showing no improvement and the Air Force version actually showing
in its flight test that it too had very serious deficiencies and would not
meet Air Force requirements, there was more data appearing in the trade press
about the problems that were going on and more word started reaching the congressional
committees.In 1967,the Congress during the appropriation and budget process
refused to commit any production funds for the F-111B after Adm. Connolly
in a hearing finally made a statement, which Jerry Miller relates in a
"Foundation" article, to the effect that there's not enough thrust in all
of Christendom to make the airplane satisfactory.
Up to that point in time,
though, the Navy in the appropriation and budget process had gone along with
OSD and continued to support the airplane. Much earlier Tom Connolly had
made the statement that made all of us at the working level cringe when he
testified after a flight in the airplane that the airplane "flies like a
lady." There were lots of comments then about the size of that particular
lady. The game that our senior officials had to play seemed to me to be "Either
go along with us or else." The "else" being a cut of a major budget item.
Most of the OSD decisions were political affecting the F-111, not technical.
Obviously this led, after a few years, to all kinds of requests for the "lessons
to be learned" from the experience. Adm. Fawkes had asked Gloeckler and myself
to prepare something on the lessons learned and I finally wrote a memorandum
on 13 March 1967 on the subject which is pretty self-explanatory. I'll include
it as Exhibit VF-6
. The only thing I might add is that this "lesson learned" business is a
good deal more difficult than one might expect because there were damn few
lessons really that I learned other than to be more forthright, and obnoxious.
We might have been better off becoming "whistle blowers" and appearing in
the public press yelling our case rather than sticking within the system
and trying to get the airplane changed. But the guys at the top learn different
lessons than those of us at the bottom of the chain. A second memo,
Exhibit VF-7
, written slightly earlier, deals with the same subject, but with a request
initiated by then SecNav Nitze. Everything he stated as a lesson that he
had learned were things that people that had been doing airplane development
already knew. One thing that the lessons learned, as I point out in the memo,
is that the deadlines that were established and so on and the way that the
system worked were always ridiculous. We always ended up with a day or two
or even less to respond to secretarial decisions. I guess I never did suggest
that they let the working level talk directly to the policy level instead
of having several layers in between. That should have been said.
I'll continue my version
of history now with the VFAX program which of course evolved into the F-14.
Some of the early stuff on this may be of some interest and may not appear
elsewhere. In the year or two before the end of the F-111, as has been mentioned,
lots of studies were being done both in and out of the Navy some funded, some
unfunded , on how best to solve the needs of the fleet for an F-4 replacement.
The big effort finally came about when it was apparent that the F-111B was
not going to make it and the concept then became one of taking an airplane
similar to the VFAX and adding the Phoenix missile system to it. I'm not
sure how many other people were inventing that airplane at the same time
but I remember being in Fred Gloeckler's office with a group of Grumman people
for a VFAX discussion. The more you looked at the total situation the more
you became convinced that a better solution would be to get a new fighter
that would carry Phoenix and still have enough performance to do the other
fighter missions. In essence, VFAX with the addition of the Phoenix system.
Fred Gloeckler was the guy that first suggested it I believe. In short order
Grumman came up then with some studies with that kind of an airplane. They
all looked attractive. Another formal full scale study then ensued. Adm.
Zumwalt in this case was the designated leader of the study while Capt. Mike
Ames was usually my point of contact. It was a big effort. The cost effectiveness
studies that used to be done routinely in Gloeckler's shop with his small
group escalated to major efforts extending over a month or more of work with
many people involved in the whole game. The "back of the envelope" studies
were just as reliable when done by those knowledgeable in the field.
Needless to say, that
fighter study then justified the need for the new airplane, with the designation,
VFX. We had the usual trouble with OSD on setting the program up. They wanted
to approve every sentence in the specification and in the RFP. The RFP, in
trying to comply with the rules coming out of OSD at the time, got to be
two or three inch thick document rather than the half inch thick document
that we were used to. But it was decided that it was better to try to comply
with the rules than to fight the system.
Another big difference
at the time was that in the usual case we did not fund design competition
efforts. We let the contractors gamble really on who was going to get a production
contract. You got a production contract by winning the experimental contract.
This time OSD forced a funded effort for the four companies which had been
active in this design area.
We finally ended up with
contracts for development of proposals. We paid the contractors to submit
proposals for the VFX, including Grumman, North American, McDonnell Douglas
and General Dynamics. The proposals were submitted, we evaluated them, and
Grumman was a hands down winner. All of the airplanes were variable sweep
wing designs with the exception of North American. I think all of the design
studies up to that point had concurred in the fact that one got a better
airplane using variable sweep. The Navy did not agree with the performance
claims of North American. NASA generally agreed with our position, forestalling
any real controversy in the political arena.
When we started this program
the normal number of production airplanes to be bought was something like
463 with a normal production rate of eight a month or 96 a year. If we had
our way we would have had the contractor bid fixed price on six R&D airplanes
and then with production ceiling options for perhaps another 100 airplanes.
We tried to get that kind of a contract through OSD but they refused and
forced us to include fixed price ceiling options for the entire planned buy.
I felt that this was quite unreasonable. The financial risks seemed too great
for any manufacturer to assume. The program as initially laid out contemplated
we'd start the program with the TF30-P12 engines which were already in the
F-111B and fully developed, but we planned to shift over to a new engine
then under development under the management of the Air Force, a Pratt Whitney
design. It would give us a marked increase in thrust and with better specific
fuel consumption. The airplane then would be called the F-14B.
The second step envisioned
in the airplane was to install a new avionic suite that would have an all
weather attack capability built into it so that you could do the job of the
A-6 without a major increase in complexity of the system. It was a good idea,
and the technology was believed to be available. That would have been the
F-14C. The F-14C dropped out of the picture first and eventually our new
engine got cancelled as well so we were stuck for a long time then with the
engines that had been developed initially for the Missileer and then used
with an afterburner for the F-111 program.
I think its been well
publicized elsewhere that the basic design mission of the F-14 included four
Sparrows, and that the six Phoenix FAD mission would be considered an overload.
We also had the complete A-7 level of attack capability built into the system
from the beginning though that feature was dropped later. The reason for
its elimination was to reduce costs associated with flight test clearance
of Navy conventional stores at all wing sweeps. At the time, the production
program had been cut back to levels that made it appear that all the F-14s
would be needed for the pure fighter roles.
Back to the VFX competition.
The evaluation of the proposals went off very well with Grumman selected
as the winner almost hands down. However, to meet the rules that were being
handed down by OSD, it was determined that we should carry two people through
until we negotiated complete contracts. McDonnell Douglas was selected to
provide the competition for Grumman. The people that are really not involved
in the process all seem to think that competitive step is necessary, that
it keeps the first contractor honest and so on. In my experience it's a step
that just complicates the acquisition and increases total cost. The people
doing the negotiating know full well whether or not they can negotiate a
contract. If they need competition then make the decision on a case-by-case
basis to do it but don't make it a requirement and don't do the program that
they later got into of "best and final" offer where you try to make the contractor
reduce his price usually already too low. It just gets you in more trouble,
at least on major procurements.
The thing that eventually
gave us most of the contract problems in the F-14 was the variable quantity
lot requirement that we had. I probably talked about it back when we talked
about the A-7 though we had added this then in order to provide more flexibility.
If we wanted to increase the quantity of aircraft we wanted to have contractual
coverage and not have the contractor "hold us up" for larger prices than
the prices for the airplanes already under contract.
In the F-14 program what
really happened was that Grumman in pricing the variable lot quantity apparently
made the fatal assumption that their business base would continue to be the
same whether they were building 50% of the specified F-14 contract numbers
or whether they were building 150% of those numbers. So then their variation
of price with production rate was very very flat. A curve sheet that shows
the problem will be attached with Exhibit
VF-7(ed: called the Variable Lot Pricing Graph ).
. That curve sheet shows that the F-14 had about one-third the increase in
unit price when you cut the production rate in half and that the S-3 had
and one-quarter of the increase specified for the F-15. Unfortunately, these
facts were known to us at the time we negotiated the contract. I remember
distinctly talking with our contracts people and they agreed that the price
variation quoted for the reduced rate and really for the 150% rate too were
not reasonable. They informed Grumman that we believed they had a problem
with the VARLOT pricing. Grumman, after study, informed us that they didn't
agree so the clause remained as bid. It is seldom that a contracting officer
will suggest raising a bid price. It just isn't done. So in this case Grumman
was told only that there was a problem. In retrospect, we could have avoided
lots of problems if we had been more specific. It is not unlike the Air Force
telling the contractor that he had a deficiency but not telling whether it
was high or low. If I had it to do over, I think I would find a way, hopefully
ethical, to let the contractor know the specifics of our concerns. The effect
of that VARLOT mistake was huge. The unit price differential between the
normal and half production rate was so low that it invited the budgeteers
to cut the quantity of airplanes being procured, and actually they did just
that as soon as we got to the point where they could take advantage of that
contract clause. The discussion went like this: "How much does the price
go up if we only buy half as many?" "Well, it only costs another few percentage
points." "Oh, well, then let's do it, it won't break the contract." We would
have been in far better shape if we had never had at least the low side of
that variable lot pricing clause. Some years later Grumman got into trouble
with the lot 5 or 6. When they could no longer produce the airplanes for
the option price at the half rate, Grumman had another chance to recover.
I remember a trip to Grumman with Adm. Tom Connolly, Mike Ames and probably
Scotty Lamoreaux in connection with this problem. My recommendation at the
meeting was that Grumman could ask for relief under the ASPR by admitting
that they had made a mistake and that the Navy was aware that it was a mistake.
We could then treat it as a mutual mistake and rewrite that clause. For reasons
I still don't understand Grumman elected not to do that. It probably would
have created a hassle at the time but it would have saved a lot of effort
farther down the road and we might have been allowed to produce more aircraft.
Well, all and all, as
everybody knows the F-14 program went very well. To kind of indicate the
difference between the F-111 and F-14 programs, I made three trips to Grumman
on the F-14 including the visit as a member of the mockup board, while on
the F-111 program I had been forced to travel some thirty-five times for
conferences scheduled to solve problems. The F-14 went like a Navy airplane
should go. We had some problems. We recognized those problems and solved
them. Dive brakes had to be redesigned and we had a big hassle on the design
of the landing gear. We saved a few hundred pounds with a clever redesign.
All kinds of troubles were predicted on that one, but as so often happens,
when you recognize a problem, with a good detail design job you can solve
it before it appears. Well, without belaboring the point the overall development
went well. The airplane flew for the first time on December 21, 1970, a month
or two ahead of schedule.
TAPE 14 of 16,
SIDE B
The flight date was easy
for me to remember because it turned out it was my wedding anniversary. On
the day of the first flight Adm. Connolly had called on that morning after
I was at work and told me that we were going to fly up to Grumman that day.
He had the CNO airplane and Mike Ames, Scotty Lamoreaux and myself joined
Adm. Connolly and we flew to Bethpage. None of us other than the Admiral
knew the purpose of the trip. We got up there and learned that the first
flight was scheduled that afternoon. As usual, there were a few little paperwork
problems to clear and the flight was a couple of hours late. Mike, Scotty
and I waited together in a car at the edge of the airport. The pilots came
back, gave us a thumbs up and said that in their opinion they thought we
had a winner. So everybody was pretty happy. About the time then when we
started to go back to Washington the weather closed in and we had to stay
overnight. Grumman had a hastily arranged dinner party during which a telephone
call to my wife was put thorough telling her I wasn't going to quite get
back in time for our 35th anniversary.
We had a disaster on the
second flight of the airplane a short time thereafter when the airplane crashed
on final approach after a complete hydraulic failure. We eventually had to
replace all the titanium lines in the hydraulic system with stainless steel
due to resonance problems causing fatigue failure. The pilots almost brought
the airplane in before losing all their hydraulic fluid causing loss of control,
The pilots ejected at very low altitude just before the plane crashed at
the edge of the field and were not seriously injured. And of course then
the program was delayed for a few months while we solved the problem of the
hydraulic lines.
The program progressed,
I thought, normally in '71 until trouble arose in the cost area while negotiating
the target price of lot 4, undoubtedly due to that VARLOT foul-up. Somehow
or another the negotiations escalated up to the DepSecDef level with Mr. Packard
and Grumman CEO Evans. From then on, there was obvious OSD bias against the
F-14 program. Mr. Packard reached the conclusion that the airplane was too
expensive and instituted programs seeking a lower cost alternative. I was
not involved in any of those skirmishes, but I hope someone will provide
that history. Capt. Mike Ames must know.
The initial look at low
cost alternatives of course revealed the fact that there weren't any and
undoubtedly DepSecDef was told that. The second phase in low cost alternatives
came about I think during a congressional hearing when Senator Symington suggested
that we get a carrier version of the Air Force F-15. He claimed that the studies
were all available and ready to go. That turned out not to be true. The F-15
program people, Al Jarret from McDonnell came into town. He was one of the
technical guys at McDonnell on the F-15 program, but formerly was at Vought,
knew the Navy requirements well and was respected in NAVAIR. We spent the
day trying to determine the status of their F-15 Navy studies. We soon found
out that we couldn't deal directly with McDonnell. The Air Force objected.
We had to then work through the Air Force in order to get any data. At the
time Gloeckler and his group were doing a fair share of that work but eventually
we ended up with no solutions. In the end, the F-15 mod was shown to be considerably
more expensive than the F-14 so it didn't make any sense. The only real proposal
we had was for a version of the F-15 carrying four Sparrows which really put
it into the effectiveness ballpark of the F-4. Probably a little below because
it was proposed as a single seat airplane instead of a two seat airplane.
We tried to get from McDonnell Douglas a proposal to also carry the Phoenix
so we could get a more direct comparison of capability but the Air Force
informed us that McDonnell Douglas could not do that type of a job within
the time, money and resources available so we never did get a Phoenix carrying
proposal on the F-15. It seemed like the Navy conducted a thousand cost studies,
and every time we did a study, we found out it was cheaper to just buy more
F-14s than try to buy half as many and then supplement it with something
else.
About that time Clements
replaced Packard and I guess at the DepSecDef level the situation really
went from bad to worse. Clements was not a person who really understood the
aircraft business nor how we did business nor anything else. I wasn't the
only one that thought that. After one of the acrimonious episodes between
the Navy and OSD on the subject of F-14 alternatives Clements invited me
to lunch, just the two of us sat there and talked for an hour or so. He started
off by introducing himself and saying that he didn't know a damn thing about
aircraft but he sure as hell knew a lot about oil rigs, while I assured him
that I didn't know anything about oil rigs but that I did know something
about aircraft and aircraft acquisition. The meeting was very amicable and
I explained what I thought were the facts of life to him but apparently it
made absolutely no impression. From my vantage point, he continued causing
problems with every step and I didn't know whether he didn't understand what
I said or whether he was just incapable of absorbing it. Strangely, I later
talked to Ed Heinemann and he had a similar experience where he had gotten
crossways with Clements on something, went through the same kind of an exercise,
thought he'd convinced him and at the end of the game Ed walked out happy
but the next time they met on the same subject Clements was right back to
his original viewpoint. He was either incapable of being convinced by facts
or he just didn't understand the whole situation.
While we continued trying
to find alternatives, continued trying to do the program, the whole OSD
conglomerate were doing things that caused all of our programs to be studied
in detail, overdone in studies and so on and so forth. Among the various
things that I can remember now is that the high-low mix program started,
and the prototyping (with a capital P) came to the fore. Within the Navy,
Adm. Zumwalt and Tom Davies, then the R&D admiral in CNM, were pushing
the idea of the SCS, a sea control ship. Also going on were studies of the
cost of large and small carriers by NAVSHIPS probably related in part to
the SCS but also related to some VSTOL work that was going on. Some of these
things we'll have to talk about in a little more detail.
Might as well talk about
the high-low mix concept first. OSD, after they found out that there was
no single low cost alternative to the F-14, came up with the idea of a high-low
mix. The OSD opined that we didn't need one-for-one replacement of F-14s
for the F-4, but that half of the F-14s could be replaced by some lesser
capability (and cheaper) aircraft.
The whole high-low mix
thing had been started with a study by one of the think tanks. For OSD, Al
Simons, who headed up the TACAIR part of DDR&E, seemed to be the chief
sponsor. He invited us all over to hear a presentation by the think tank
after they had finished their study. The study was entitled, "Designing to
the Budget Realities." What the think tank had done was to take the long-range
plans of the services, add them together, and to their apparent surprise
found out that those total expenditures down the pike were well over current
OSD budgets. So they concluded something had to be done about it. Well, of
course this had always been true. At any time, past or future, when one added
up long-range plans the totals would exceed any current budget. The budgets
would get closer to fiscal reality in the next step when you got to the short-range
plans. Something like the FYDP, the five-year plan then in effect in the
Pentagon, and then you really got into fiscal reality when you did each year's
budget. But in any event the study ended up by saying that perhaps a way
to solve the whole problem was to buy some high capability aircraft to meet
high capability threats and then to buy a bunch of low capability aircraft
to meet the low capability threats. To them it made sense. To all of us the
idea appeared extremely naive, particularly for carrier aviation. Against
our high threats it was going to take everything we had and then some. The
other side may not be willing to send their JV squad against us so that the
fracas can be rated a toss up.
The thing that was most
disturbing I think to all of us was that all of these kind of ideas came
along with no real study of effectiveness to see whether they would work.
On the other hand, every time we made a move or offered a new program we
had to define it in the greatest of detail from a cost effectiveness standpoint.
They, OSD, the bad guys in my book, never did. After I retired I got around
to writing a couple of papers on the high-low concept which were published
in two different magazines. I'll talk about them later when I get around
to discussing the acquisition process, but my generalized study convinced
me that the cost of a 50-50 mix was substantially higher than buying an equal
number of the better aircraft.
The other thing that was
being pushed to a great degree was prototyping. For some reason there are
people who believe that prototyping will solve all of our problems. We had
given up prototyping before World War II because it cost too much, took too
long, and really wasn't necessary with the state of the art at that time.
But some of these people, that had really not been involved before, seemed
to say that prototyping would solve not only all known technical problems
but also all known fiscal problems. Again, while we all considered it ridiculous,
it cost us an enormous amount of time. That lesson of history is almost universally
ignored.
Well the high-low thinking
of course impacted on us with OSD starting to say we didn't need the Phoenix
capability. The Marines complicated the problem by jumping in and out of
the program -- one year they were in, next year they were out. When they were
in, the replacement of their F-4s when added to the Navy's replacement required
something like 729 airplanes. When the Marines dropped out the numbers dropped
considerably.
In early '73 Clements
appointed an ad hoc committee headed by Dr. Flax who was well-known and usually
well respected man in the aero field. He had headed the Cornell Aero Labs,
had a good reputation and most people liked him. Clements asked the group
to look into the modernization program of naval aircraft. The Flax committee
report, as well as all other studies, said that we needed something better
than the F-4 but the Flax group also wanted something less expensive than
an F-14. We would have been happy too to get F-14 capability with less cost
but we didn't know how to do it, then or now.
Sometime in the spring
of '73 I made the decision to retire, not because I really wanted to but
I had already been working a year or two too long if I wanted to optimize
my retirement annuity. The retirement system provided that if you continued
to work you gained two percentage points each year on the percentage of your
salary that you would receive as the annuity. If one retired, however, you
received a cost of living increase each six months plus one percentage point
to take care of the fact that COLAs, so-called, were always six months late.
It didn't pay to continue working. My friend Fred Gloeckler had retired a
year earlier. Also Gil Weiss, my old buddy that had come down and been my
assistant ever since I had been in the bureau had retired even earlier. It
didn't make financial sense not to leave, particularly when I had no desire
to move into the industry side of the acquisition game.
Well, despite the fact
that I was retiring I continued to work on the project at hand -- I guess
the problem at hand was really DepSec Def Clements. He finally sent us a memo
on the 7th of June, a copy of which I'll mark Exhibit VF-8
. It's a memo for the Secretary of the Navy concerning the fighter modernization
program which directs us to look at a prototype program that he had studied.
Actually it wasn't quite as bad in the 7 June version as it had been slightly
earlier. By this time he had narrowed down the things that we were to study
to versions of both the F-14 and the F-15 and some kind of a modified F-4J
and we were supposed to show him -- let's see what he said we were supposed
to do -- "The Navy will develop for my approval management, development, test,
production and funding plans for these aircraft which will include" , and
so on. We were to get this back to him by the 13th of June so he had given
us one week to do the study. Fortunately of course we had been doing so many
of these exercises that we were able to put it together quickly. Those of
us at the working level of course didn't have anything like a week because
our answer had to be put together, go to the CNO, CNO to the Secretary of
the Navy, Secretary of the Navy to Secretary Clements. Well, the whole thing
was so stupid that I guess I blew my stack again.
Then on the 11th of June
after we had complied with the request as well as we could, I found that
I couldn't get anybody to take any official action on the total problem.
I ended up writing a memo from me to Secretary of the Navy protesting the
whole scheme. A copy is attached as Exhibit VF-9
. I sent the memo direct to SecNav, hand-carried it to his office, but sent
copies to CNO, CNM, OP-05, COMNAVAIR, his deputy and to my immediate boss
AIR-05. I was still trying to work somewhat within the system. Well, most
of the people that were involved in between either said nothing to me immediately
or telephoned and said, "Great idea. Let's see what happens." All except Ike
Kidd, then CNM, who was not pleased and directed me to go get my memo back.
I wasn't about to do that so I said no thanks and told him I'd prefer to
let the memo stand. He apparently then called Adm. McClellan, COMNAVAIR and
directed him to retrieve my memo. Someone did, because CNM's copy was returned
to me. Unfortunately, SecNav Warner was out of town so he didn't become aware
of the situation until later.
There was another part
of the exercise which had increased my frustration. Mr. Clements had requested
funding estimates for his prototype scheme including development, testing
and production. NAVAIR prepared the data and forwarded them either to or
via CNO. We were then told that the total package was not desired, but only
the prototype plan figures were to be forwarded. That made no sense to us,
but NAVAIR complied. From our viewpoint, a rational decision on the OSD plan
could only be made by totaling the three individual prototype plans plus
the production costs of the selected prototyped model plus the production
costs of the reduced numbers of F-14s, and comparing that to the normal F-14
costs.
The problems all were
headed for a climax in a hearing scheduled for 19 June before the TACAIR
subcommittee of the Senate Armed Services Committee. In preparation for the
hearing, the staff of the committee requested a meeting with Navy representatives.
Adm. McClellan headed a small group, including me, in response. OSD had sent
two individuals, apparently to monitor the conference. In response to the
staff's request for cost information on the proposed DepSecDef F-14 Alternatives/
Prototype Plan, they were given the official correspondence which contained
only the prototyping costs. After the OSD monitors departed, the staff asked
Adm. McClellan whether he had any data on the total cost picture. Adm. McClellan
said he had been directed not to have the numbers so he didn't have any.
The staff guys apparently anticipating the answer then asked the rest of
us and when they got to me I had the numbers. So we provided the numbers
on what our estimates were for doing the Clements-directed program of prototyping,
two years later make the decision, put into production and so on. Then we
compared it with just buying more F-14s, which, of course, was the cheaper
way to go, as well as being much more capable.
On the basis presumably
of the fact that the committee didn't think that the actual numbers would
be given to them, nor would the working level recommendations ever reach
them they requested that I be an official witness as opposed to just being
a backup at the hearing. They knew that backups could be told not to show
up while witnesses had to appear unless they were excused by the committee.
On the morning of the
meeting I got a phone call from CNO's office, Adm. Mickey Weisner was then
OP-09 and was acting CNO. He asked me to join Adm. McClellan and to come
over to SecNav's office. We of course complied. At SecNav's office we went
over the whole issue with Secretary Warner. He had read my memo before Adm.
McClellan and I arrived. He agreed that the thing didn't make any sense so
he said to us, "You stay here. I'm going to go see Mr. Clements," which he
did. We sat and waited. Eventually about twenty minutes before hearing time
he telephoned us and said proceed to the Old Senate Office Building and I
will meet you there. So Adms. Weisner, McClellan and I got into a car and
off we went. On the way to the building Mr. Warner and Mr. Clements caught
up to us and signalled that they wanted to say something so riding side by
side on the SW freeway, Warner told Weisner not to go inside but to remain
outside and not let me go inside. So we did as directed and met Secretary
Warner outside and Warner said that Clements had decided I should not appear.
Clements would explain to the committee why and that they could call me as
a witness later. So I went back to the office. They went ahead and held their
19 June 1973 hearing. In that hearing Mr. Clements had no statement to give,
but told the committee that he'd work from prepared notes. The prepared
notes and his non-existent statement appeared in the hearing record later.
He said that after he had studied the fighter modernization program he reached
the conclusion that the Navy didn't need Phoenix capability in all of its
airplanes and that there were no lower cost alternatives that the Navy had
found so he was embarking on a prototype program to determine what was the
best non-Phoenix carrying airplane to go with the Phoenix carrying F-14.
He still wanted the Navy to prototype a stripped F-14 and to get an F-15
carrier suitable airplane from McDonnell to prototype and he'd drop the idea
of prototyping a F-4 upgrade (which of course had never made any sense to
us). He defended his program in the usual manner of "preliminary data, more
later, etc." The testimony from Warner and Adm. Weisner was less adversarial
about the prototype program than I hoped. Well they didn't really argue against
the program but concentrated on supporting the budget request of 50 F-14s.
As usual Clements had pretty well cut their feet out from under them by saying
that everybody was in agreement and that the Navy was supporting the program.
I knew personally that they did not but somehow or another in these things
it's very difficult to get crossways with the Secretary of Defense. It shouldn't
be, but it is.
I went ahead and retired
officially on 23 June, the day after my 61st birthday. Three days
later I appeared at a hearing before that same committee where I gave them
my ideas and my version of history and what we should and what we should
not do. This was the '73 version. The hearing was not well attended. Senator
Goldwater and Senator Cannon I believe were there at the beginning. Goldwater
stayed around for a while but most of the questioning ended up by being done
by Charlie Cromwell with all the senators missing. This was usually the case.
If the secretaries and admirals weren't there the Senators didn't appear.
Strangely, though, the hearing report reads as though all the senators were
present and there was a lively colloquy. My statement to the committee is
attached as Exhibit VF-10
. It is a good summary of the prototype program and contains whole cost data.
Well the outcome of that exercise was that the Congress refused to fund the
Clements prototype program so I guess I considered that we won a small victory
but we sure hadn't won the ball game.
From that point on --
bear in mind now I'm out of the Navy and the idea of using less than a one-to-one
replacement of our F-4s was still in being. The total number of airplanes
being talked about then was in the low 300s.
After I retired I was
approached to see if I wouldn't continue in a rehired annuitant role. In
that role I could work part-time, primarily to provide consulting services
to my old office and I would be paid the difference, on a daily basis, between
what my daily rate of the full salary had been and what my annuity would
turn out to be. The going rate was, I believe, $105 a day then for a consultant
but because of my rehired annuitant status, the actual pay was about $45
per day. A few years later it was about $5 or $10 a day because the COLAs
kept increasing the annuity and so the annuity kept getting closer and closer
to the salary at which I had retired.
A brief recap then as
to where we were at the time of my retirement. Grumman had produced or had
agreed to produce through lot 5 on the contract something on the order of
122 airplanes. They were being produced at the minimum contractual rate of
48/year. They had refused to build lots 6 and 7 under the terms of the contract
because they would have gone bankrupt. They later negotiated a new contract
price. That 122 airplanes was through fiscal year '73. The overall program
had been cut back as OSD directed. We had to go to one squadron per carrier
instead of the two that had always been planned. At that time the Marines
were back in the program after dropping out earlier. The studies all said
that if we were to complete the VF modernization, that is replace all the
F-4s, if we were to do that without any production gaps we needed 174 more
F-14s in fiscal years through '77. So we would have had then a total in the
program of about 400 F-14s.
The new engine that we
were supposed to get in airplane number 68 had been, or was in the process
of being, cancelled and the later GE-101 engine hadn't come along far enough
yet that it was being actively considered.
From an acquisition policy
standpoint, forcing Grumman to fixed price ceilings for 463 airplanes, normal
quantity, that we had done in the original contract was obviously a mistake.
It had been forced upon us by OSD however. As I believe I had said before,
we should have held the fixed price ceiling requirement to only about 100
aircraft. That would have been more or less equivalent to the 200 that we
had on the A-7 program and the 100 that we had on the CH-53 program. When
you try to go too far the system falls apart. The contractor should not have
to risk his entire company.
That's the story of the
low cost alternatives to the F-14. It will be apparent to anyone with even
a moderate background of airplane design that the program pushed by OSD had
absolutely no hope of success.
TAPE 15 of 16,
SIDE A
At this point we probably
should take a step backward and examine the lightweight fighter program for
the Air Force which eventually really impacted on the way the F-14 program
went from 1973 on. The "Prototyping with a capital P" program, as it was
dubbed by Adm. Suerstedt, started in the early seventies. OSD had again endorsed
the thought that prototyping would solve all problems. Industry in general
tended to support it at least in the trade press. I suppose people that supported
it were the have-nots, those companies that had no programs going.
Anyway, in the early seventies
OSD went to all the services and asked them to submit possible projects for
inclusion in the new Prototype program. Many people thought in a wishful
thinking kind of a way that the dollars involved in the Prototype program
were going to be extra dollars and wouldn't come out of our normal budgets.
Adm. Suerstedt ended up being our representative on the Prototype program
and after lots of discussion the Navy eventually ended up with their number
one priority program that we would like to see funded was the S-3 COD Program.
We hadn't been able to get it funded in the normal budget process so some
thought that this ploy might work.
In addition, a bunch of
smaller programs mainly in the electronics field were included. Some ASW
work, sonobuoys and some AEW work too I believe. The Air Force submitted
their list of things and about half way down the list of perhaps ten projects
was a lightweight fighter. The lightweight fighter scheme of course had been
promulgated by the "gum on the windshield" fighter types in and out of the
Pentagon for a long time. Those people of course were part of the background
noise that confused everything that was going on in the real world. It seemed
obvious and even more obvious I guess in retrospect, that what the Prototype
program may have been designed to do was to get a lightweight fighter started.
So the one that really got funded in this big program was the lightweight
fighter for the Air Force. It was set up to be a very simplistic kind of
an airplane. Minimum fighter requirements and minimum control by the Air
Force. The airplane would have no radar in it, armed with gun and Sidewinder,
short radius, maximize the dog fight capability. In the source selection
the primary requirement or criteria for the selection was to minimize life
cycle cost. To that end, the rules of the competition strongly emphasized
use of an engine already in service. In actuality, it pretty well boiled
down to that if you were going to win the competition you had better have
the F-100 engine that was already in the F-15 program in your airplane.
It was apparent to me
that the Air Force was kind of in a bind because they had looked at lightweight
fighters when they set up the requirements for their F-15 and had rejected
them. Their choice of F-15 requirements seemed to be to get the most capable
fighter possible which would not conflict with the F-14. Those of us in the
Navy thought that the airplane in reality probably didn't offer much over
the F-4 program at least as far as air to air capability. They obviously
could not get a new program of their own if it was going to be in the ballpark
with the F-14 so they picked the best one they could.
When the lightweight fighter
then came along they obviously didn't want that to be an F-15 competitor as it turned
out to be for us. The Air Force actually stated that the light fighter program
was solely a technology program with no production contemplated. It was only
to investigate concepts, new technology and so on. Well, they ended up by
getting proposals from General Dynamics, Vought -- then called LTV -- Boeing,
Northrop and Lockheed, all with the F-100 engine. Northrop
also submitted a twin engine design using GE J-101 engines.
The Air Force, after the
proposals were in, invited the Navy to come out and take a look so perhaps
four or five of us went out, I among them. Whitey Feightner was there I remember,
probably Lamoreaux, not very many. In the very brief look we were given at
the proposals it seemed fairly obvious that Kelly Johnson at Lockheed had
just ignored all the rules and tried to build the best airplane he could
that would be, let's say a replacement for the F-104. It did have a reasonable
capability with enough fuel to have a decent ra |